Background to the project:
Agnico Eagle developed its ventilation and backfill infrastructure in the underground mine
Shaft:
4 ventilation shafts from 95m-685m, 4.1m diameter plus a media hole for refilling.
Performed by rig:
Rhino 2000
Background to the project:
Agnico Eagle developed its ventilation and backfill infrastructure in the underground mine
Shaft:
4 ventilation shafts from 95m-685m, 4.1m diameter plus a media hole for refilling.
Performed by rig:
Rhino 2000